Press and News

August 25, 2016

PRESIDENT SIRLEAF INSPECTS PROGRESS OF THE MT. COFFEE HYDRO POWER PROJECT SITE – Pays 3rd Visit

For the 3rd time on Monday, August 15, 2016, the President of the Republic of Liberia, H E Ellen Johnson Sirleaf paid a one-day visit to […]
August 12, 2016

MT. COFFEE HYDROPOWER REHABILITATION PROJECT (MCHPP) GIVES BACK TO COMMUNITIES: Training in improved health and sanitation practices, construction of 15 new wells and hand pumps, and rehabilitation of 5 existing

As part of its commitment to environmental and social responsibility in the Mt. Coffee affected communities, the Mt. Coffee Hydropower Rehabilitation Project has identified the provision […]
May 23, 2016

LEC/PIU still accepting applications for Contracts Control Manager

The Terms of Reference for the position can be accessed here.
March 22, 2016

LEC Announces Survey and Resettlement Action Plan for the Buzzi Quarter Island at the Mt. Coffee Site

PUBLIC ANNOUNCEMENT — March 22, 2016   Survey and Resettlement Action Plan for the Buzzi Quarter Island at the Mt. Coffee Hydropower Plant in Harrisburg   […]
February 25, 2016

Public Announcement: Public Consultation and Construction on Transmission Lines

Monrovia, Liberia February 22, 2016   Public Announcement for the Mt. Coffee Hydropower Rehabilitation Project: Public Consultation and Construction on Transmission Lines   The Government of […]
January 6, 2016

President Sirleaf Tours Mt. Coffee Project Site

The President of the Republic of Liberia, Madam Ellen Johnson Sirleaf, on Friday December 18, 2015 undertook a tour to inspect the progress of ongoing works […]
June 9, 2015

LEC Signs contract with DAWNUS International Ltd. of the UK for Main Civil Works of Mt. Coffee Hydropower Plant

Monrovia – June 8, 2015: The Liberia Electricity Corporation (LEC) on May 27, 2015 signed a contract with DAWNUS International Ltd, a company based in the […]
May 18, 2015

LEC Signs Contract with ELTEL NETWORKS of Sweden

Monrovia – May 13, 2015   The Liberia Electricity Corporation (LEC) has on May 6, 2015 signed a contract with ELTEL, a Sweden-based provider of technical […]
April 8, 2015

LEC Signs Contract with Joint Venture of Pan African Engineering Group, Sigma Group Inc., and Mamba Point Hotel for Camp Construction Works and Camp Services

Monrovia – April 8, 2015   The Liberia Electricity Corporation (LEC) has on April 8, 2015, signed a contract with the Joint Venture of Pan African […]